At the top of Bridge Street, landscaping crews at the former Los Amigos site plan to move dirt along the bike path. Over on Vail Road, flaggers are guiding traffic around underground boring at 17 Vail Road, and the old FirstBank building there is about to come down. Both crews are working against the same deadline, and the contract doesn't set it. Snow does.
That idea explains Vail Village's fall construction schedule. The work runs to the ski calendar. The Town's Weekly Construction Update for Oct. 12, 2026 shows it project by project. One crew is pushing to finish before snowmaking starts. One project has already moved its exterior work to spring. Two others will still be active on Opening Day.
The deadline is the snowmaking, not the calendar
The team renovating The 62 at 278 Hanson Ranch Road is "pushing to complete the remaining work before snowmaking operations begin on the mountain," according to the Town's Oct. 12 update. That sentence sums up the season. Once the guns start on Vail Mountain, exterior work at the base of the slopes gets harder to schedule and harder to justify.
The Town code builds in a deadline of its own. Vail Code § 8-1-21 bars street openings and pavement cuts in the public way between Nov. 15 and April 15. Between Nov. 15 and Dec. 15, Public Works can make an exception for special circumstances or for public utilities. After Dec. 15, a permit can be issued only in an emergency or by resolution of the Town Council. The same section sets normal hours for permitted work at 7 a.m. to 7 p.m., Monday through Friday, or as the Town's annual Vail Construction Hours Policy provides.
Mountain Haus at 292 E. Meadow Drive shows what happens when a project doesn't make the cutoff. The Sept. 28 update set Nov. 12 as the start of exterior work on the building's new entry. Two weeks later, the Oct. 12 edition said only interior lobby work was under way and the exterior work "is now expected to occur in the Spring." The update gives no reason for the change. The original Nov. 12 start would have fallen one day before Opening Day.
Where each fence stood on Oct. 12
All dates below are the Town's projections from its Oct. 12 update, not promises.
| Project | Address | Status on Oct. 12 | What the Town expects |
|---|---|---|---|
| Base Camp | 298 Hanson Ranch Road | New deck and exterior work done | Full wrap-up by end of October; occasional vehicle access |
| The 62, formerly Los Amigos | 278 Hanson Ranch Road | Interior renovation and exterior landscaping | Completion in early November |
| PNC Bank/Prima Residences | 17 Vail Road | Underground electrical boring; demolition next | Boring through Oct. 23; demolition mid- to late October; work inside the fence from Nov. 12 |
| Condo building | 281 Bridge Street | Exterior and interior work ongoing | Completion in late December |
| Mountain Haus new entry | 292 E. Meadow Drive | Interior lobby work | Exterior work in spring |
The projects fall into three groups. Base Camp and The 62 are trying to finish before the lifts open. 17 Vail Road and 281 Bridge Street will keep working into the season, under tighter limits. Mountain Haus has put its exterior off until the snow melts.
The corner that changes most before Opening Day
Over the next three weeks, 17 Vail Road will see more change than any other site in the village. In the Oct. 12 update, the Town said underground electrical boring started Sept. 28 and would continue until Oct. 23, depending on underground conditions. Crews were working from the south side to limit the impact on the intersection, with flaggers on site during working hours.
The same update said community deliveries for FedEx, UPS, Amazon and other services would soon move temporarily from Vail Road to W. Meadow Drive, with signs directing drivers. It expected demolition of the existing building in mid- to late October, lasting about 10 days. On those dates, the building may be coming down this week.
Nov. 12 is the date to remember. From then on, the Town expects all work to stay inside the construction fence. Temporary ADA-compliant crosswalks and pedestrian rerouting near the Fire Station and the Chapel will be added as needed. That is the day before Opening Day on Nov. 13. The boring and demolition are scheduled to be finished before the lifts start turning. The project will keep going behind a fence all winter.
The site is the former FirstBank building. The Town's Sept. 14 update describes the new structure as four high-end condominiums, bank space on the first floor, a new deed-restricted unit and underground parking. The Town's updates don't yet say when the bank space will open.
Neighbors with questions can reach Leonard Sandoval, the Town's construction area coordinator, at 970-390-4677.
At the top of Bridge Street, a family name returns
The 62 is the project with the deepest roots in Vail Village. When Vail Daily first profiled it in February 2025, founder Brad Kaemmer described it as a dining and social club named for 1962, the year Vail opened. It would serve breakfast, lunch, après and dinner to members and the public, with a casual dress code.
The Kaemmer family has been on this block before. Vail Daily reported that his parents once owned La Piñata, the restaurant that became Los Amigos. The family also owned Pistachio's, which later became Vendetta's, and opened The Toy Shop on Bridge Street. Kaemmer told the paper he planned to name the bar Donovan's Copper Bar, after the bar longtime local John Donovan used to run. The club's plans also include ski-in, ski-out access, ski valet and boot storage for members.
That 2025 story set a summer 2026 debut. The schedule has since slipped, and the sources don't agree on where it stands. In an Aug. 25 post on the club's own site, Kaemmer wrote that its doors were "now officially open" for its first ski season. The Town's Oct. 12 update still lists a full renovation under way inside the fence, with deliveries limited to morning hours on Hanson Ranch Road and the top of Bridge Street, and completion projected for early November. Either way, the building has to be finished before the snowmaking starts.
Next door at Base Camp, the new deck and exterior improvements are done. Vehicles may still come and go as needed until the project is fully wrapped up, which the team hopes will happen by the end of October. On the Gore Creek Drive side of Bridge Street, the condo building at 281 Bridge Street is going through a resurfacing, roof replacement and interior remodel. The Town projects completion in late December. That puts the building past Thanksgiving and into the holiday season.
The days the work must stop
The projects that keep going into winter face a second set of limits. Each weekly update lists "No Work Days" for holidays and special events. The Oct. 12 edition lists these for the rest of 2026:
- Vail Mountain Opening Day, Nov. 13
- Thanksgiving Day, Nov. 26
- Vail Kris Kringle Market in Vail Village, Dec. 10 through 13
- Christmas Week, Dec. 24 through 31
The list grew between editions. The Oct. 5 update showed only the Sunday farmers market, Opening Day and Thanksgiving. The Kris Kringle Market and Christmas Week first appear in the Oct. 12 version. All summer, the Sunday Vail Farmers Market & Art Show was a no-work day too, through Oct. 4. Through the holidays, the Town's event calendar decides when the sites go quiet.
The protected dates line up with the biggest crowds in the village: the first lift day, the holiday market, and the week between Christmas and New Year's. For 281 Bridge Street, a late-December finish means stopping for the Kris Kringle Market and then running right up to Christmas Week. If that slips, the next window opens after Dec. 31.
The street-cut restriction in § 8-1-21 is written into the Town code, and the no-work list is published every week. This post is general information about those published rules, not legal advice. Anyone with a project of their own should confirm how the rules apply with the Town of Vail and the right professional.
The Town posts a new construction update every week. Each edition covers the next round of demolition dates, fence lines and detours on Vail Road, Hanson Ranch Road and Bridge Street.
If you own in Vail Village and want to know how one of these projects might affect your building, your rental calendar or a sale you're planning for this winter, contact Led for a private, no-pressure property consultation through Led Gardner.